Silver, Research

Silver developers compared: Tonopah West, El Tigre and Calico

A side-by-side reference of study level, price assumptions, economics and capital for three North American silver projects.

November 5, 2026

This page pulls the main figures from each company’s most recent published study into one table. All figures are company reported and in US dollars. They are not directly comparable, because each study uses different price assumptions and sits at a different level of engineering.

Project summary

MeasureTonopah WestEl Tigre StockworkCalico
CompanyBlackrock SilverSilver TigerApollo Silver
LocationNevadaSonora, MexicoCalifornia
Latest studyPEA, 2026PFS, 2026PEA, 2026
StatusEconomic studyUnder constructionEconomic study
Base case silverUS$31/ozUS$38/ozUS$55/oz
Base case goldUS$2,700/ozUS$3,200/ozGold domain excluded from plan
After-tax NPV (5%)US$437MUS$456MUS$737M
After-tax IRR28%65.7%25%
Mine life11.2 years10 years15 years
Initial capitalUS$190.4MUS$86.8M in study, US$124M current budgetUS$633M

Resources

MeasureTonopah WestEl TigreCalico
Higher confidence40.2 Moz AgEq indicated235.5 Moz AgEq measured and indicated115.6 Moz Ag measured and indicated
Inferred83.0 Moz AgEq78.9 Moz AgEq51.5 Moz Ag

Silver equivalent and pure silver figures are not the same thing, and El Tigre’s resource covers the wider property, not only the Stockwork Zone under construction.

How to use this page

Use it to see what kind of project each one is, and where to look next. Check the linked releases and the technical reports before relying on any figure, since studies get updated. We revisit this page when a new study is published.

Companies in this piece: Blackrock Silver Corp., Silver Tiger Metals Inc., Apollo Silver Corp.

Sources

  1. Blackrock Silver: updated preliminary economic assessment, Mar 31, 2026
  2. Silver Tiger: El Tigre construction update, Oct 20, 2026
  3. Silver Tiger: MD&A for the period ended June 30, 2026
  4. Apollo Silver: Calico preliminary economic assessment, Oct 29, 2026