Silver developers compared: Tonopah West, El Tigre and Calico
A side-by-side reference of study level, price assumptions, economics and capital for three North American silver projects.
November 5, 2026
This page pulls the main figures from each company’s most recent published study into one table. All figures are company reported and in US dollars. They are not directly comparable, because each study uses different price assumptions and sits at a different level of engineering.
Project summary
| Measure | Tonopah West | El Tigre Stockwork | Calico |
|---|---|---|---|
| Company | Blackrock Silver | Silver Tiger | Apollo Silver |
| Location | Nevada | Sonora, Mexico | California |
| Latest study | PEA, 2026 | PFS, 2026 | PEA, 2026 |
| Status | Economic study | Under construction | Economic study |
| Base case silver | US$31/oz | US$38/oz | US$55/oz |
| Base case gold | US$2,700/oz | US$3,200/oz | Gold domain excluded from plan |
| After-tax NPV (5%) | US$437M | US$456M | US$737M |
| After-tax IRR | 28% | 65.7% | 25% |
| Mine life | 11.2 years | 10 years | 15 years |
| Initial capital | US$190.4M | US$86.8M in study, US$124M current budget | US$633M |
Resources
| Measure | Tonopah West | El Tigre | Calico |
|---|---|---|---|
| Higher confidence | 40.2 Moz AgEq indicated | 235.5 Moz AgEq measured and indicated | 115.6 Moz Ag measured and indicated |
| Inferred | 83.0 Moz AgEq | 78.9 Moz AgEq | 51.5 Moz Ag |
Silver equivalent and pure silver figures are not the same thing, and El Tigre’s resource covers the wider property, not only the Stockwork Zone under construction.
How to use this page
Use it to see what kind of project each one is, and where to look next. Check the linked releases and the technical reports before relying on any figure, since studies get updated. We revisit this page when a new study is published.
Companies in this piece: Blackrock Silver Corp., Silver Tiger Metals Inc., Apollo Silver Corp.