Silver Tiger Metals Inc.
TSX: SLVR, OTCQX: SLVTF. Under construction, Sonora, Mexico. Silver, Gold.
Building the Stockwork Zone mine at its wholly owned El Tigre silver and gold project in Sonora, Mexico.
Overview
Silver Tiger approved construction of the El Tigre Stockwork Zone in March 2026 and moved to the Toronto Stock Exchange that May. It is targeting commissioning and first pour in December 2027.
El Tigre
Northeastern Sonora, Mexico. Under construction.
A 100% owned property of about 215 square kilometres, around 90 kilometres south-southeast of Agua Prieta. The 2026 prefeasibility study on the Stockwork Zone uses a base case of US$38 per ounce silver and US$3,200 per ounce gold.
| After-tax NPV (5%) | US$456 million |
|---|---|
| After-tax IRR | 65.7% |
| Mine life | 10 years |
| Initial capital in the PFS | US$86.8 million |
| Current capital budget | US$124 million |
| First pour | Targeted December 2027 |
Our coverage
- El Tigre’s budget moved from US$87 million to US$124 million. Here is what is built so far.
- Same metal, three price decks: why silver study headlines are hard to compare
- Silver developers compared: Tonopah West, El Tigre and Calico
News releases
- Oct 20, 2026: Provides an El Tigre construction update
- Sep 21, 2026: Announces $87 million financing and a capital cost update
- Mar 18, 2026: Awards the construction management contract