Silver, Quick Insight

El Tigre’s budget moved from US$87 million to US$124 million. Here is what is built so far.

Silver Tiger’s October update shows the road done, earthworks early and first pour still targeted for December 2027.

November 3, 2026

Silver Tiger’s 2026 prefeasibility study put initial capital for the El Tigre Stockwork Zone at US$86.8 million. The company’s October construction update now gives a total capital budget of US$124 million, after a capital cost update in September.

Budgets moving between a study and a build is common. The more useful question is how much of the work is actually locked in.

Where the build stands

As of October 20, the company reported about US$72 million committed and about US$24 million spent, with roughly US$120 million of cash on hand. The 46 kilometre access road is complete, clearing is complete, and long lead equipment has been procured. Detailed engineering is 70% done and the permanent camp is 72% done.

Earthworks are earlier in the process, at 14% for the heap leach, ponds and process plant platforms and 23% for the crusher and ancillary platforms.

What to watch

Commissioning and first pour remain targeted for December 2027. Earthworks progress and the civil works contract are the next markers, since they will show whether the schedule and the new budget are holding.

Companies in this piece: Silver Tiger Metals Inc.

Sources

  1. Silver Tiger: El Tigre construction update, Oct 20, 2026
  2. Silver Tiger: financing and capital cost update, Sep 21, 2026
  3. Silver Tiger: MD&A for the period ended June 30, 2026